Design and supply of 8no. 108 tonne self climbing jump form systems for construction of the main pylons. The H frame pylons sloped at 5 degrees and tapered in two directions.
OM Engineering is grateful for the support and backing of the Australian Government and Efic, the department for Australian Exporters Finance.
Schedule
Construction of the pylons commenced July 2015 and all 8 piers were completed by Jan 2017.